Madrid Water Tank Project
SUMMARY OF WORK
The Madrid Water Tank Project is located on NMSR 14 just south of Madrid, NM in Santa Fe County, New Mexico. The project area (see Sheet No. 3) is on private surface ownership in Section 25, Township 14 North, Range 07 East (USGS 7.5’ Madrid Quadrangle).
This project involves construction of a new 125,000 gallon water tank and new 8” water line along NMSR14, connecting to an existing 8” waterline for increased fire flow. Four phases will be completed:
- Preparation and construction of tank pad area. Build up and compact a new water tank pad for construction of new tank. PH corrective soil must be provided as the top layer of soil for the tank pad. Material may be stockpiled just north of the tank pad site. (see Sheet 12) Tank pad slopes to be stabilized with 3”-4” fractured rock over Mirafi fabric or equal.
- Tank foundation completed by contractor based on design from tank provider and tank to be completed by tank provider.
- New 8” water line to be constructed for new tank to existing water line on east side of arroyo. (see Sheet 5). Water line to be jack & bored under NMSR 14 at location shown on Sheet 4. The water line crossing under the arroyo may be open trenched, weather permitting, at location shown on Sheet 5. The new water line is to be connected to the existing water line, also shown on Sheet 5.
- The new tank is to be connected to the existing well as shown on Sheet 3. Reseed any disturbed areas and replace any fence removed/damaged during construction.
Demobilization shall be conducted in such a manner to ensure that the Contractor leaves all project areas in as good or better condition than before disturbance.
NEPA Public Meetings/Notices | |||
Notice Type | Date & Time | Type of Meeting | Attendance List |
Environmental Assessment | January 25, 2024 August 15, 2024 |
Public Comment/Notice |
Secifications, Maps and Images | ||
Specifications | ||
Madrid Water Tank Project Manual | ||
Figures | ||
All Figures |
Bids | ||
Sealed Bid Opening | Pre-Bid Opening | |
NM STATE PURCHASING DIVISION
|
MANDATORY PRE-BID CONFERENCE
* In person pre-bid conference will be held in Madrid, NM at the Mine Shaft Tavern (2846 NM-14, Madrid NM). From the meeting place, the group will travel 0.4 miles south on NM-14 to the water tank turnoff (located at approximately 2801A NM-14, Madrid, NM). The site visit is expected to take between two to three (2-3) hours, including travel to and from the meeting site. Prospective Bidders must provide their own transportation to the site.
GEOTECHNICAL REPORTS * Western Technologies Final Madrid Geotechnical Evaluation Report
Questions and Answers
|
|
Administrative and Technical Questions and/or Comments Administrative: Leeland Murray @ 505.629.9677 or leeland.murray@emnrd.nm.gov Technical: Leeland Murray @ 505.629.9677 or leeland.murray@emnrd.nm.gov |
Completion of Contract |
Year Completed: Cost: $ Project Engineer: Tierra West/Mike Tompson, P.E. Project Manager: Leeland Murray |