GR010RE Tyrone Mine, Revision 09-1
GR010RE Tyrone Mine – Regular, Existing Mining Operation – Revision 09-01 Updated Closure/Closeout Plan (CCP)
GR010RE Tyrone Mine
Tyrone Mining Inc.
Copper, Grant County
03-2021 Revision 09-1 Approval
12-2020 Financial Assurance Proposal
11-2020 FMI Response to Public Comments
09-2020 Letter, Technically Approvable
08-2020 Update on Collateral
08-2020 GRIP Comments
08-2020 Public Meeting Presentations
MMD Presentation
FMI Presentation
GRIP Presentation
08-2020 Letter from GRIP Withdrawing Request for Public Hearing
07-2020 Notice for Virtual Public Meeting on August 5, 2020
06-2020 MMD Comments on Closure/Closeout Plan Update
04-2020 Tyrone Closure/Closeout Plan Update, Revised April 2020
Cover Letter
Text, Figures, Plates and Tables
Appendix A – Reclamation Design Drawings
Appendix B – Facility Characteristics Forms
Appendix C – Earthwork Cost Estimate Report
Earthwork Cost Estimate – Excel spreadsheets
Appendix D – Basis of Cost Estimate for Water Management and Treatment
Cost Estimate – Excel spreadsheets
Appendix E – Characterization and Volumetrics
Appendix F – Tyrone Stockpile Stability Analysis
01-2020 Joint Agency Response to NPV Calculations
01-2020 FMI Response to Comments
12-2019 MMD Comments on Cost Estimate
07-2019 Tyrone Closure/Closeout Plan Update, Revised July 2019, Revision 09-01
Text, Figures, Plates and Tables
Appendix A – Reclamation Design Drawings
Appendix B – Facility Characteristics Forms
Appendix C – Earthwork Cost Estimate Summary Report
Cover letter, with Attachment 1A and 1B
Earthwork Cost Estimate – Excel spreadsheets
NPV – Excel spreadsheets
Appendix D – Basis of Cost Estimate for Water Management and Treatment
Cost Estimate – Excel spreadsheets
Appendix E – Characterization and Volumetrics of Cover Materials
Appendix F – Tyrone Stockpile Stability Analysis
05-2019 Cost Estimate
04-2018 FMI Response to Comments on Updated CCP Revision 09-01
12-2017 Comments on CCP, Revision 09-01
12-2013 MMD letter granting Public Hearing, Revision 09-01
11-2013 Public Notice Documentation, Revision 09-01
10-2013 Request for Public Hearing, Revision 09-01
07-2013 Tyrone Closure/Closeout Plan Update, Revision 09-01
Text
Figures
Plates
Tables
Appendix A
Appendix B
Appendix C
Appendix D
09-2012 Reclamation Cost Estimate Update, Revision 09-01
04-2009 Permit Revision 09-01, Closeout Plan Update
Closeout Plan Revision Cover Letter
Closeout Plan Certification
Closure / Closeout Plan Update (dated 10-11-2007)
Cover Letter
Cover Page
Closeout Plan Update
Tables
Figures
Plate 1: Mine Units & Facilities
Plate 2: Tailing Area Characteristics & Facilities
Plate 3: East Mine Unit Characteristics & Facilities
Appendix A: Design Drawings
Appendix B: Facility Characteristics Form
Appendix C: Earthwork Cost Estimate
Appendix D: Water Management & Treatment Cost Estimate
Appendix E: Additional Studies
Abatement Plan and Addendum
Comprehensive Cover Performance Evaluation
3X Tailing Annual Summary
3X Tailing As-Built
No. 1 Stockpile Annual Summary
No. 1 Stockpile As-Built
Stability Analysis & Study
Pit Perimeter
1A and 1B Stockpiles
1C and 7A Stockpiles
2A, 2B and 3A Stockpiles
4C Stockpile
Borrow Source Materials Investigation
Preliminary Report & Addendum
Supplemental Materials Characterization Study
Interim Report and Final Report
Seepage Investigation Report
Interim Report and Final Report
Supplemental Ground Water Study
Work Plan for Ground Water Modeling
No. 3 Tailing Pond Assessment Update
Tailing Transport & Deposition Impacts
Sludge Handling Plan & Cost Estimate
Work Plan for Surface Impoundments Study
Process Solution Elimination Study & Response to Comments
Work Plan for Feasibility Study
Discharge Elimination
Mine Dewatering
Municipal Sewage Sludge
Sanitary Effluent No. 2 Dam
Seepage from No. 1X Dam
Seepage from Little Rock Mine
Affected Areas Study
Wildlife Monitoring Plan
06-2008 FMI Responses to Issues on Updated CCP, Revision 09-01
04-2004 Permit Revision 01-01